GDOT Responds to Questions Following Board Meeting

As promised, listed below is GDOT’s response to CORR’s questions about the 411 Connector. The meeting took place immediately after GDOT’s October board meeting.

The cost estimate documents GDOT provided did not support the State Transporation Improvement Program (STIP) cost projection for the road, so we are following up to clarify that information before posting it.  Please check back soon (in this blog post) for the latest cost estimate information.

Q & A (directly from GDOT’s deputy press secretary):

Specifically related to the 411 Connector project (661950), how much notification will a property owner be given that they may be affected by the act of eminent domain and/or condemnation?

Once the Department authorizes right-of-way (RoW) funds, the Department will hold a property owners meeting within a few months.  Then individuals that own property that is required for the road will be contacted individually to begin the acquisition process.

Where in the “re-evaluation” process is the existing environmental documentation?

There are two items remaining on the re-evaluation:

1) The potential of acidic soil that may affect the [Cherokee] darter fish species investigation. [This study] is almost complete and will be to submitted to U.S. Fish and Wildlife Service.

2) The study of the Dobbins Mine for historic significance and will not be completed until April 2011.

Once both have been completed, the re-evaluation will be submitted to FHWA for approval, perhaps in May 2011.

What is the status of the additional analysis that they believe is being conducted to determine the effect of acid drainage from excavation of Dobbins Mountain into the water/stream system?

The soil borings have been completed and the response to U.S. Fish and Wildlife is being drafted.

The TIP documents they have show three related projects – 008842, 008843 and 008844.  They want to know what these projects are, how they are related to the big project, and if the funds associated with these three projects are separate from, or included in, the $182 million listed on project 661950 construction?

Those three project numbers were for tracking earmarked RoW funding that is now included in Project No. 661950 total.

Where are all of the above projects in the funding process?  Have funds been identified and allocated already, or are they on a long-term future list with no funding?

RoW acquisition funding is programmed and that acquisition is scheduled to begin this fiscal year (2011).  Construction funding is not programmed as yet.

Why is GDOT tearing down a mountain and displacing eagles (birds), instead of just going around?

We are not doing either of these things.  This route represents the most cost effective use of taxpayer resources while protecting the environment and fulfilling the project’s need and purpose.

The group believes GDOT’s district office is removing their protest signs from private property.  They say they visited the office and saw their signs in the back of GDOT pick-up trucks.  They want an explanation of why GDOT is removing their signs placed on private property – said they have asked the property owners for permission to place them.

This issue arises every election season.  We have neither the resources nor the interest level to remove signage from private property.  We are required by law, however, to remove signs illegally placed within state right of way.

Share

CORR Attends October GDOT Board Meeting

This week members of Coalition for the Right Road (CORR) attended the Georgia Department of Transportation’s monthly board meeting to register opposition against the agency’s preferred design, Route D-VE. The route will cost state taxpayers more than $280 million and is plagued with several environmental and road design issues.

Approximately, 40 residents and supporters – dressed in red shirts and with stickers affixed to their clothes – made the trip from Cartersville to seek answers about this ill-fated project from GDOT District Representative David Doss, Chief Engineer Gerald Ross and/or Project Manager Albert Shelby. Conveniently, they were not available to comment or answer questions for a few minutes after the meeting.  However, the group did get the opportunity to speak with GDOT’s deputy press secretary and asked several questions. Once CORR receives answers to those questions, we will post them on the website.

Overall, the trip was a great success and kept the pressure on. To attend future GDOT board meetings (possibly in November or December), please email us at US411connector@gmail.com. Transportation to the board meeting is provided.

(For those that attended, CORR thanks you for your continued support.)

CORR members listen to questions about 411 Connector

 

 

 

 

 

 

 

 

 

 

Share

CORR Attends 42nd Annual Great Locomotive Chase Festival and Parade

CORR members (in green) took part in last weekend’s parade in Adairsville.

This past weekend, Coalition for the Right Road (CORR) participated in the 42nd Annual Great Locomotive Chase Festival and parade in Adairsville.

The festival, held at the Adairsville Historic Square, included arts and crafts booths, food and entertainment, pageants, street dances and Gospel singing. Special activities were also hosted inside the depot at the Age of Steam Rail Depot Museum. CORR members were able to share information on the negative impact U.S. 411 Route D-VE would have on Bartow County.

CORR members also took part in the annual parade, driving and walking through downtown, waving banners that read “There’s Another Way” and “Stop D-VE.”

To voice your concerns about Route D-VE, sign our petition or share your opinions on Facebook or Twitter. If you are interested in attending future events or joining CORR, email us at us411connector@gmail.com.

Share

Follow

Get every new post delivered to your Inbox.